Foothill Expressway and Arboretum Drive intersection improvements
Last updated: 05/14/2024 - 14:00
Project limits
Intersection of Foothill Expressway and Arboretum Drive in Los Altos.
Project description
The project provides operational and safety improvements. Work will include:
- Modifying traffic signals which will include, installing new signal poles, new traffic signal controller and service cabinets, upgrading pedestrian push buttons to make them contactless and accessible for the blind, and installing pedestrian motion sensors
- Upgrading existing pedestrian curb ramps to comply with current Americans with Disability Act (ADA) standards
- Repaving the intersection within the project limits
- Installing new pavement striping and markings
Project schedule
Signal switchover will take place on 5/18/24 followed by street paving from 5/22/24 to 5/24/24. Please expect delay and plan your trip accordingly.
- County has received necessary permits. Construction is in progress and complete approximately in June 2024.
Funding source
- Construction Road Fund
Project location
Located in City of Los Altos at intersection of Foothill Expressway and Arboretum Drive.