Bear Creek Road Site 2
Last updated: 03/01/2024 - 16:05
Project location
Bear Creek Road just south of Green Mountain Retreat entrance (approx. 2.1 mi south of CA-17)
Project description
A culvert failure resulted in the formation of a sinkhole in the southbound lane. The permanent repair will involve the replacement of the existing culvert located approximately 25 feet down and the restoration of the roadway.
Project timeline
- Damage identified: Early January 2023
- FHWA approval: Late November 2023
- Consultant retained: TBD
- Design work initiated: TBD
- Design finalized: TBD
- Project advertised: TBD
- Contract awarded: TBD
- Construction start: TBD
- Construction complete: TBD
Current status
Pending consultant selection
Project documents (reports, plans, etc.)
Pending